Still waiting on the builder & the Vessels to ship from China
The decorating and building of walls is still ongoing as are the electrics, we are hopefully getting the builders on site in the next week or two to start on the drains and sloping floors. The vessels from China have not yet shipped, when they ship I’d guess at 6-8 weeks on the sea followed by however long it takes to clear through customs at Liverpool Docks.
Still to do are things like ordering all the pipework and associated valves for plumbing up the glycol chiller system for cooling fermenting vessels and cold store before getting some guys on site to fill & commission the installation, not to mention a load of pipe insulation and brackets that needs fitting.